Existence of A Concluded Contract – Is a Sine Qua Non in a claim for compensation

Section 7 of the Contract Act, 1872 provides that in order to convert a proposal into a contract, the acceptance must be absolute and unqualified. The existence of a concluded contract is a sine qua non in a claim for compensation for loss and damages under Section 73 of the Contract Act arising out of a breach of contract. If instead of acceptance of a proposal, a counter – proposal is made, no concluded contract comes into existence.
In U.P. Rajkiya Nirman Nigam Ltd. v. Indure (P) Ltd., also related to a proposal and counter-proposal. Holding that no concluded contract had come into existence, the Hon’ble Apex Court held as under:
“As seen, the material alterations in the contract make a world of difference to draw an inference of concluded contract.” Vedanata Ltd. v. Emirates Trading Agency LLC, (2017) 13 SCC 243.